Henderson Park Schedule
Henderson Park Aerial View
Henderson Park Site Analysis
Public Meeting #1 Agenda
Public Meeting #1 Meeting Minutes
January 20,
2010 (Concept Plan Presentation)
Documents provided by Ms. Moody. Click on each
link to open document.
Sign In
Public Meeting #2 Agenda
Public Meeting #2 Meeting Minutes
Public Meeting #1 Community Input
Concept 1
Concept 2
Dog Park Locations
February 22,
2010 (Final Public Input Meeting)
Documents provided by Ms. Moody. Click on link to open document.
Final Master Plan
The next steps
are to prepare the construction documents required to build.
September 12,
2010
-
Revonda Moody,
the project manager with DeKalb County Parks and Recreation Department
and the Henderson Park master plan, transferred in May to a new
project management role with Parks Operations. Ms.
Moody will continue to work with communities about Park improvements,
including Henderson Park, and will also oversee the
Porter Sanford III Performing Arts & Community Center.
On behalf of the Henderson Park community, we’d like to thank Ms.
Moody for her leadership and guidance with the Master Plan. She
has transitioned the Henderson Park Master Plan to her colleague, John
Bateman. Revonda Moody’s contact information: 404.294.2890
or rnmoody@dekalbcountyga.gov
John
Bateman’s contact information is: 404.687.3542 or
jwbateman@dekalbcountyga.gov
-
Once the plans are approved for
permit, DeKalb County purchasing & contracting will release the plans
for Invitation to bid to contractors. It is anticipated, the
advertisement for bids will be released by late September and
anticipated construction to start early 2011.
Sources:
Revonda Moody,
DeKalb County Parks & Recreation
Marti Watts,
Silverman Construction Program Management
November 11,
2010
Update from Henderson Road neighbor, Yared:
"There seems to
be some very good news about HP. First I finally talked to John (the
current project manager) and he informed me that while things seems to
be slow, they are moving along; the project was approved by the
development office and in the process of to being advertised for a bid
for construction in the next 30-60 days. More importantly, as you see
from the summary from the DeKalb County Board of Commissioners meeting
and from what John said, a substantial amount of money, in addition to
what was available initially (about 150,000) will be devoted to this
project. This will be a significant progress that will allow the
county to complete much of the project initially. Please pass this
good news to others. Yared"
BOC Agenda
Summary from November 9, 2010 Meeting:
Board of
Commissioners – District 1
G2. To
Recognize and Appropriate 2001 Park Bond District 1 Funds of $380,000
to the To Recognize and Appropriate 2001 Park Bond District 1 Funds of
$380,000 to the Henderson Park Development Project (Accepted to the
Regular BOC Meeting agenda) - APPROVED